FSL Projects Ltd provided Bank Monitoring Services on behalf of Barclays. The funding provided for new office accommodation for Premtech split over two floors. The development was being completed by developer CWC who commissioned the lump sum contract on behalf of Premtech.
With Premtech not having overall control of the build process, it was incumbent on FSL Projects to ensure their requirements were being accepted and addressed throughout the course of the works.
Overall, the project was a huge success and progressed with very limited issues. As with many projects, delays with a utility provider caused the biggest concern, however, proactive input from Premtech enabled the installation to be completed prior to handover.